Wyoming NEVI Build-Out
Every NEVI-funded charging site in Wyoming, from grant award to first charge. Part of the regional NEVI tracker.
Wyoming's NEVI pipeline is at an earlier stage — sites here are moving from award to permitting to construction, and expected live dates should be treated as approximate. The pattern matches the program's purpose: corridor gaps with real traffic and thin commercial incentive.
New to the program? Start with NEVI Explained — what the $5 billion program requires (97% uptime, four 150 kW ports minimum), why it paused and restarted in 2025, and how to tell if a station is NEVI-funded.
Wyoming Sites
Data sources and methodology
Site list sourced from state DOT NEVI program pages and FHWA grant records, cross-checked against the NREL Alternative Fuels Station Locator. Status verified monthly. Expected live dates are official estimates and regularly slip 3–12 months. For scoring methodology across the site, see how we measure. Related: Wyoming EV charging hub · Q3 2026 regional status report.