NEVI Build-Out Pennsylvania

Pennsylvania NEVI Build-Out

Every NEVI-funded charging site in Pennsylvania, from grant award to first charge. Part of the regional NEVI tracker.

46
Sites tracked
46
Live
0
Under construction
206
Planned ports

Pennsylvania's NEVI pipeline is at an earlier stage — sites here are moving from award to permitting to construction, and expected live dates should be treated as approximate. The pattern matches the program's purpose: corridor gaps with real traffic and thin commercial incentive.

New to the program? Start with NEVI Explained — what the $5 billion program requires (97% uptime, four 150 kW ports minimum), why it paused and restarted in 2025, and how to tell if a station is NEVI-funded.

Pennsylvania Sites

Location Corridor Operator Ports Power Status Expected Live Source
Altoona Electrify America 4 150 kW live † 2025-08-26 Source →
Aston Tesla 8 250 kW live † 2024-09-17 Source →
Bowmansville APPLEGREEN 4 250 kW live † 2026-04-10 Source →
Breezewood FCN 4 150 kW live † 2025-11-14 Source →
Bristol Electrify America 4 150 kW live † 2026-06-27 Source →
Brookville ChargePoint Network 2 250 kW live † 2025-04-24 Source →
Brookville ChargePoint Network 2 250 kW live † 2025-04-24 Source →
Carlisle FCN 4 150 kW live † 2025-02-20 Source →
Chambersburg FCN 4 150 kW live † 2025-02-01 Source →
Columbia FCN 4 150 kW live † 2026-04-16 Source →
Drums SWTCH 4 250 kW live † 2026-01-20 Source →
Edinboro FCN 4 150 kW live † 2026-03-17 Source →
Emlenton ChargePoint Network 1 150 kW live † 2023-09-22 Source →
Emlenton ChargePoint Network 1 150 kW live † 2023-09-22 Source →
Fort Littleton Tesla 8 250 kW live † 2025-05-29 Source →
Hunker APPLEGREEN 4 250 kW live † 2026-01-06 Source →
Jonestown ChargePoint Network 2 250 kW live † 2024-11-21 Source →
Jonestown ChargePoint Network 2 250 kW live † 2024-11-21 Source →
Kylertown FCN 4 150 kW live † 2025-03-21 Source →
Meadville Tesla 12 250 kW live † 2025-06-12 Source →
Mercer FCN 4 150 kW live † 2025-11-16 Source →
Mifflinville ChargePoint Network 2 250 kW live † 2025-04-12 Source →
Mifflinville ChargePoint Network 2 250 kW live † 2025-04-12 Source →
Mill Hall eVgo Network 4 150 kW live † 2025-03-14 Source →
Monroeville eVgo Network 6 150 kW live † 2025-07-24 Source →
Mountain Top ChargePoint Network 1 150 kW live † 2026-05-22 Source →
Mountain Top ChargePoint Network 1 150 kW live † 2026-05-22 Source →
Mountain Top ChargePoint Network 2 250 kW live † 2026-06-06 Source →
Muncy Electrify America 4 150 kW live † 2026-05-19 Source →
New Castle Tesla 8 250 kW live † 2025-04-23 Source →
New Stanton Electrify America 6 250 kW live † 2026-02-17 Source →
Newburg FCN 4 150 kW live † 2025-11-27 Source →
Oxford ChargePoint Network 2 150 kW live † 2026-03-12 Source →
Oxford ChargePoint Network 2 150 kW live † 2026-03-12 Source →
Pittsburgh eVgo Network 8 150 kW live † 2025-09-30 Source →
Pittsburgh ELECTRIC_ERA 4 150 kW live † 2026-04-21 Source →
Pittston eVgo Network 6 150 kW live † 2023-12-22 Source →
Sewickley Electrify America 4 150 kW live † 2025-12-19 Source →
Shrewsbury Tesla 12 250 kW live † 2025-11-14 Source →
Slippery Rock ChargePoint Network 2 250 kW live † 2024-12-12 Source →
Slippery Rock ChargePoint Network 2 250 kW live † 2024-12-12 Source →
Somerset Tesla 10 250 kW live † 2014-01-10 Source →
Summerdale Tesla 8 250 kW live † 2025-06-06 Source →
Upper Darby Electrify America 4 250 kW live † 2026-07-01 Source →
Woodlyn Tesla 12 250 kW live † 2026-03-20 Source →
York Electrify America 4 150 kW live † 2025-07-15 Source →

Data sources and methodology

Site list sourced from state DOT NEVI program pages and FHWA grant records, cross-checked against the NREL Alternative Fuels Station Locator. Status verified monthly. Expected live dates are official estimates and regularly slip 3–12 months. Last data check: August 2026. For scoring methodology across the site, see how we measure. Related: Pennsylvania EV charging hub · Q3 2026 regional status report.

= station auto-added from NREL's funding_sources: NEVI tag, not editorially verified against state DOT records. Hand-curated entries take precedence.