NEVI Build-Out Ohio

Ohio NEVI Build-Out

Every NEVI-funded charging site in Ohio, from grant award to first charge. Part of the regional NEVI tracker.

19
Sites tracked
19
Live
0
Under construction
82
Planned ports

Ohio's NEVI pipeline is at an earlier stage — sites here are moving from award to permitting to construction, and expected live dates should be treated as approximate. The pattern matches the program's purpose: corridor gaps with real traffic and thin commercial incentive.

New to the program? Start with NEVI Explained — what the $5 billion program requires (97% uptime, four 150 kW ports minimum), why it paused and restarted in 2025, and how to tell if a station is NEVI-funded.

Ohio Sites

Location Corridor Operator Ports Power Status Expected Live Source
Austinburg eVgo Network 4 150 kW live † 2024-11-10 Source →
Beaverdam eVgo Network 4 150 kW live † 2024-08-29 Source →
Belmont eVgo Network 4 150 kW live † 2024-11-22 Source →
Burbank eVgo Network 4 150 kW live † 2024-11-16 Source →
Byesville FCN 4 150 kW live † 2024-07-04 Source →
Caldwell eVgo Network 4 150 kW live † 2024-11-29 Source →
Canton eVgo Network 4 150 kW live † 2024-11-09 Source →
Cridersville FCN 4 150 kW live † 2024-06-25 Source →
Findlay eVgo Network 4 150 kW live † 2024-11-16 Source →
Franklin eVgo Network 6 150 kW live † 2024-11-29 Source →
Jeffersonville eVgo Network 4 150 kW live † 2024-12-21 Source →
Kent eVgo Network 4 150 kW live † 2026-01-23 Source →
London eVgo Network 4 150 kW live † 2023-12-08 Source →
Marengo eVgo Network 6 150 kW live † 2024-06-13 Source →
New Philadelphia FCN 4 150 kW live † 2024-11-27 Source →
North Canton eVgo Network 6 150 kW live † 2025-01-14 Source →
Troy eVgo Network 4 150 kW live † 2026-01-23 Source →
West Chester eVgo Network 4 150 kW live † 2026-01-23 Source →
Zanesville FCN 4 150 kW live † 2024-11-27 Source →

Data sources and methodology

Site list sourced from state DOT NEVI program pages and FHWA grant records, cross-checked against the NREL Alternative Fuels Station Locator. Status verified monthly. Expected live dates are official estimates and regularly slip 3–12 months. Last data check: August 2026. For scoring methodology across the site, see how we measure. Related: Ohio EV charging hub · Q3 2026 regional status report.

= station auto-added from NREL's funding_sources: NEVI tag, not editorially verified against state DOT records. Hand-curated entries take precedence.